Your company, Deep Rock Mining LLC, is considering an expansion of operations into iron ore mining. Your engineers have just completed a 6-month survey designed

Your company, Deep Rock Mining LLC, is considering an expansion of operations into iron ore mining. Your engineers have just completed a 6-month survey designed to determine whether or not a viable mining operation can be mounted on a particular piece of land. This survey cost $500,000 to complete. The results of the survey, along with several other pieces of information, are detailed below:

Survey Results

:Your engineers estimate that there are 650,000-700,000 tons of recoverable iron ore underneath this land.

Investment in CapEx:

If you choose to move forward with the project, you will need to invest in several new pieces of mining equipment. The cost of this new equipment is $10,000,000.This equipment will need to be manufactured to your specific needs. Design and construction of this equipment will take one year.Payment is due upon delivery of the new equipment to your site at the end of this year.Once the equipment is built, it will need to be transported and installed onsite at an additional cost of $1,500,000.An additional $500,000 will need to be spent to prepare the site itself for the installation of the new equipment. This includes grading the land, running electrical and water lines, ensuring proper drainage, and making sure all environmental requirements are followed.

Operations:

After the equipment has been installed on site at the end of Year 1, mining operations will commence in Year 2. Your team estimates you can produce 125,000 tons of ore in the first year of mining operations.The amount of ore produced will remain constant for the first four years of operations at 125,000 tons per year.Beginning with the 5thyear of mining operations, as the easier-to-access ore becomes more scarce, your team estimates that the amount of ore produced will begin to decrease by 60% per year, relative to the year prior. This will continue for three years.After the 7thyear of mining operations, it is estimated that the mine will no longer be viable and will be shut down.

Accounting Assumptions:

For the purposes of this analysis, the price of ore is assumed to remain constant for the life of the project. Iron ore currently sells for $125/ton.The operating costs to extract the ore are estimated to be $70 per ton for the life of the project.In addition to the variable operating costs just outlined, there will be additional fixed costs of $750,000each year the active mining operations are taking placeif you move forward with this project.The investment in equipment and any appropriate associated costs will be depreciated straight-line over 7years, to an assumed salvage value of zero for accounting purposes. Despite the depreciation assumptions stated earlier, you expect that, at the end of the projects life, you will be able to sell the equipment involved in the project for $2,000,000.During the first year of the project, while the mining equipment is being built, the project will require an additional investment in net working capital of $1,000,000. This level of working capital will remain constant for the life of the project. At the end of the projects life, the full amount of this working capital will be recovered (reduced to $0).The tax rate is assumed to be 30%. Your firms cost of capital is 14%.All revenues and expenses will be accounted for and recognized at the end of the period in which they take place.

Based on the above information, answer the following questions:

1.Forecast the incremental free cash flows that will result from an investment in this project using template below please.

Year 0 1 2 3 4 5 6 7 8

Revenue

Cost of Prod (COGS)
Gross Profit
SG&A
R&D
Other Expenses
Depreciation
EBIT
Income Tax
Incremental Earnings
PLUS: Depreciation
LESS: CapEx
LESS: Increase in NWC
Salvaged Equip Cash Flow
Free Cash Flows

2.Based upon the cash flows calculated in question 1, what is the NPV of this project?

3.A significant source of uncertainty in this project lies in the base case assumptions made surrounding the prevailing price of iron ore, assumed to be $125/ton, and the costs of production, assumed to be $70/ton.Perform the following sensitivity analysis to give your board a better sense of just how much margin for error there is in this project.

a.Holding all other assumptions constant, what is the NPV break-even price of iron ore for this project.? Put another way, what price of iron ore must be realized throughout the life of this project to result in an NPV of zero?

b.Holding all other assumptions constant, what is the NPV break-even level of production costs?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Financial Management

Authors: I.M. Pandey

3rd Edition

0071333428, 978-0071333429

More Books

Students also viewed these Finance questions

Question

Identify the cause of a performance problem. page 363

Answered: 1 week ago