Your company operates a steel plant. On average, revenues from the plant are $30 million per year. All of the plants costs are variable costs
Your company operates a steel plant. On average, revenues from the plant are $30 million per
year. All of the plants costs are variable costs and are consistently 80% of revenues, including
energy costs associated with powering the plant, which represent one quarter of the plant's costs,
or an average of $6 million per year. Suppose the plant has an asset beta of 1.25, the riskfree rate
is 4%, and the market risk premium is 5%. The tax rate is 40%, and there are no other costs.
a. Estimate the value of the plant today assuming no growth.
b. Suppose you enter a long-term contract which will supply all of the plant's energy needs for
a fixed cost of $3 million per year (before tax). What is the value of the plant if you take this
contract?
c. How would taking the contract in (b) change the plant's cost of capital? Explain.
I would like to know how to get the cost of capital for B. What is the formula used to find cost of capital for B after we find the Energy cost after tax.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started