Your estimated costs aren't exactly going as per the plan , so you arrived at a new cost metric to track your project progress as
Your estimated costs aren't exactly going as per the plan , so you arrived at a new cost metric to track your project progress as per only the costs involved. You have now decided to estimate the remaining costs of your project as per the current cost trend (not schedule), what would be the new estimate at completion for the remaining work at hand when the below values are given. BAC = 12000$, SPI = 0.8, CPI = 0.6 Question 11 options: 15000$ 21000$ 18000$ 20000$