Your estimated time to complete the project is not acceptable. In an attempt to reduce the time, you are considering crashing. Assume the following information
Your estimated time to complete the project is not acceptable. In an attempt to reduce the time, you are considering crashing. Assume the following information to be true about your project. Which activity will you choose to crash first?
Task | Critical | Normal Cost | Normal Time | Crash Cost | Crash Time |
---|---|---|---|---|---|
A | YES | $200 | 3 | $400 | 2 |
B | YES | $450 | 5 | $870 | 1 |
C | NO | $450 | 6 | $600 | 4 |
D | NO | $300 | 3 | $510 | 1 |
E | YES | $600 | 6 | $900 | 4 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started