Your manager recently gave you the responsibility of selecting the next project, which you will manage as the project manager. There are currently 3 projects
Your manager recently gave you the responsibility of selecting the next project, which you will manage as the project manager. There are currently 3 projects on hold to choose from. Using the weighted scoring models method, you determine that Project A has a weighted score of 16, Project B has a weighted score of 14, and Project C has a weighted score of 17. Which project do you choose and why?