Your office building is undergoing minor renovations. The entire project is scheduled to last 1 6 weeks at a total cost of $ 2 5
Your office building is undergoing minor renovations. The entire project is scheduled to last weeks at a total cost of $ It is eight weeks into the project and your manager asks you whether the project is on schedule. You plan to use various analysis techniques to determine the status.
You plan to measure project progress by comparing the actual performance against planned performance as documented in the schedule and cost baselines. What method will you use?a EVb ACc PVd EVM
According to your baselines, you expected to complete $ worth of work by the end of the eighth week. What is the term for this information?a ACb EVc PVd SV
According to your status reports, you've completed of the work so far. Based on this information, what is the EV
How do you determine the AC for your project?
Given the PV EV and SV values that you know, what actions should you take at this point? Choose two.a Bring it to the attention of the CCB with some possible solutions.b Use it to decided whether a corrective action is needed.c Investigate the root cause of the variance.d Bring it to the attention of the project stakeholders.
What is the SV for your project, how did you calculate it and what does it indicate?
What is the SPI for your project, how did you calculate it and what does it indicate?
What should you do with the results of your performance measurement analysis?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started