Your plant operates 16 hours per day, but your machinery is only staffed 8 hours per day.The average throughput rate is 30 batches per day,
Your plant operates 16 hours per day, but your machinery is only staffed 8 hours per day.The average throughput rate is 30 batches per day, and the setup time is 5 minutes per batch. The machine has no idle time.
A)What is the cycle time per batch?
B) What is the average processing time per batch?
C) If the batch size is 20 units, what is the average processing time per unit?
D)If the batch size is 40 units, what is the MTT?