Your program's actual obligations are almost exactly at their planned levels, but your program's actual expenditures appear to be lagging significnantly behind plan. Which of
Your program's actual obligations are almost exactly at their planned levels, but your program's actual expenditures appear to be lagging significnantly behind plan. Which of the following is NOT a potential cause of this problem?
A. Contractor submitting invoices several months after performing work
B. Administrative Contracting Officer is not certifying invoices in a timely manner
C. Disbursing office has changed payments to the wrong fund cite
D. Procuring Contracting Officer is awarding contracts as planned
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started