Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Your project administrator has summarized the changes to the Project Budget Report for this week. Pending Budget Changes have been approved for the following line

image text in transcribed

image text in transcribed

Your project administrator has summarized the changes to the Project Budget Report for this week. Pending Budget Changes have been approved for the following line items: Move from Pending Budget Changes to Budget Modifications Temporary Electricity $664 Asphalt Pavers $9,137 Flashing and Sheet Metal $5,275 Wood Flooring $3,027 The following new Potential Change Orders (not yet approved) have been identified for the following line items: Add to Pending Budget Changes Site Demolition $727 Brick $8,728 Heavy Timber Construction $7,224 Ducts and Diffusers $5,260 Add to Approved CO's The following new Change Orders have been approved for the following line items: Architectural Metal Fabrication $9,820 Prefabricated Chimney $7,418 Purchase Orders have been issued for the following line items: Move from Pending Cost Changes OR Forecast to Complete to Committed Costs Plant Maintenance $6,324 Door Hardware -$820 Note that no other costs are anticipated in this line item. Subcontract has been issued for the following line items! Move from Pending Cost Changes OR Forecast to Complete to Committed Costs Wiring Devices $2,436 Note that no other costs are anticipated in this line item. Cost Code Description (2) Original Budget (3) Budget Modifications (4) Approved COs (5) Revised Budget (6) Projected Budget (8) Committed Costs (9) Direct Costs (10) Projected Costs (12) Cost Difference (15) Cost Deviation (16) 0.14 0.48 Temporary Electricity Site Demolition Backfilling Asphalt Pavers Plant Maintenance 0.27 0.62 0.33 Brick 0.49 $42,830.10 $21,250.49 $14,441.96 $321.09 $18,791.85 $26,784.64 $68,392.76 $15,485.25 $9,051.44 $4,013.86 $6,960.44 $6,120.93 $43,323.38 $11,433.91 $289,202 $11,940 $11,984 $8,581 $7,191 $3,097 -$2,140 $13,055 $8,425 $12,370 -$3,157 $9,763 $3,963 $7,570 $11,253 $103,895 0.34 Pending Budget Changes (7) $664 $12,574 $7,317 $9,137 -$3,429 -$2,179 $4,396 $11,055 $5,275 $12,687 $3,027 $12,751 -$312 $399 $73,362 $14,978 -$3,831 $1,089 $403 $3,251 $388 -$645 -$2,892 $1,494 -$3,269 $12,144 $4,596 -$3,345 -$3,292 $21,069 $69,748 $29,403 $24,112 $7,915 $25,140 $25,033 $80,803 $21,018 $22,915 -$2,412 $28,867 $14,680 $47,548 $19,395 $414,166 $70,412 $41,977 $31,429 $17,052 $21,711 $22,854 $85,199 $32,073 $28,190 $10,275 $31,894 $27,431 $47,236 $19,794 $487,528 Architectural Metal Fabrication Heavy Timber Construction Flashing and Sheet Metal Door Hardware Wood Flooring Prefabricated Chimney Ducts and Diffusers Wiring Devices Totals Pending Cost Changes (11) $11,274 $7,468 $4,461 $4,773 $578 -$3,250 -$2,850 $4,702 $5,668 $7,099 $10,088 -$4,033 -$2,820 $6,089 $49,247 -$2,425 $3,824 $4,269 $13,436 -$3,269 $5,070 $4,350 $9,252 -$1,438 $10,646 $6,674 $8,708 $13,257 $14,152 $86,506 -$3,717 $8,021 -$3,474 -$3,974 $8,066 $14,258 $12,597 $7,910 $14,794 $444 $3,823 $3,938 $13,733 $11,144 $87,563 Forecast Estimate to Cost at Complete Completion (13) (14) $4,449 $9,581 $887 $20,200 $3,101 $8,357 -$3,716 $10,519 $1,753 $7,128 -$4,767 $11,311 $14,777 $28,874 $14,017 $35,881 $6,669 $25,693 $8,516 $26,705 $12,216 $32,801 -$3,887 $4,726 $11,830 $36,000 $2,145 $33,530 $67,990 $291,306 $5,132 $19,313 $5,256 $14,235 $5,375 $16,078 $14,097 $21,864 $19,024 $18,189 $20,585 $8,613 $24,170 $31,385 $223,316 -$60,831 -$21,777 -$23,072 -$6,533 -$14,583 -$11,543 -$56,325 $3,808 -$2,497 $16,430 $907 -$22,705 -$11,236 $13,736 -$196,222 1.12 0.91 2.60 1.03 0.17 0.76 1.69 0.60 Your project administrator has summarized the changes to the Project Budget Report for this week. Pending Budget Changes have been approved for the following line items: Move from Pending Budget Changes to Budget Modifications Temporary Electricity $664 Asphalt Pavers $9,137 Flashing and Sheet Metal $5,275 Wood Flooring $3,027 The following new Potential Change Orders (not yet approved) have been identified for the following line items: Add to Pending Budget Changes Site Demolition $727 Brick $8,728 Heavy Timber Construction $7,224 Ducts and Diffusers $5,260 Add to Approved CO's The following new Change Orders have been approved for the following line items: Architectural Metal Fabrication $9,820 Prefabricated Chimney $7,418 Purchase Orders have been issued for the following line items: Move from Pending Cost Changes OR Forecast to Complete to Committed Costs Plant Maintenance $6,324 Door Hardware -$820 Note that no other costs are anticipated in this line item. Subcontract has been issued for the following line items! Move from Pending Cost Changes OR Forecast to Complete to Committed Costs Wiring Devices $2,436 Note that no other costs are anticipated in this line item. Cost Code Description (2) Original Budget (3) Budget Modifications (4) Approved COs (5) Revised Budget (6) Projected Budget (8) Committed Costs (9) Direct Costs (10) Projected Costs (12) Cost Difference (15) Cost Deviation (16) 0.14 0.48 Temporary Electricity Site Demolition Backfilling Asphalt Pavers Plant Maintenance 0.27 0.62 0.33 Brick 0.49 $42,830.10 $21,250.49 $14,441.96 $321.09 $18,791.85 $26,784.64 $68,392.76 $15,485.25 $9,051.44 $4,013.86 $6,960.44 $6,120.93 $43,323.38 $11,433.91 $289,202 $11,940 $11,984 $8,581 $7,191 $3,097 -$2,140 $13,055 $8,425 $12,370 -$3,157 $9,763 $3,963 $7,570 $11,253 $103,895 0.34 Pending Budget Changes (7) $664 $12,574 $7,317 $9,137 -$3,429 -$2,179 $4,396 $11,055 $5,275 $12,687 $3,027 $12,751 -$312 $399 $73,362 $14,978 -$3,831 $1,089 $403 $3,251 $388 -$645 -$2,892 $1,494 -$3,269 $12,144 $4,596 -$3,345 -$3,292 $21,069 $69,748 $29,403 $24,112 $7,915 $25,140 $25,033 $80,803 $21,018 $22,915 -$2,412 $28,867 $14,680 $47,548 $19,395 $414,166 $70,412 $41,977 $31,429 $17,052 $21,711 $22,854 $85,199 $32,073 $28,190 $10,275 $31,894 $27,431 $47,236 $19,794 $487,528 Architectural Metal Fabrication Heavy Timber Construction Flashing and Sheet Metal Door Hardware Wood Flooring Prefabricated Chimney Ducts and Diffusers Wiring Devices Totals Pending Cost Changes (11) $11,274 $7,468 $4,461 $4,773 $578 -$3,250 -$2,850 $4,702 $5,668 $7,099 $10,088 -$4,033 -$2,820 $6,089 $49,247 -$2,425 $3,824 $4,269 $13,436 -$3,269 $5,070 $4,350 $9,252 -$1,438 $10,646 $6,674 $8,708 $13,257 $14,152 $86,506 -$3,717 $8,021 -$3,474 -$3,974 $8,066 $14,258 $12,597 $7,910 $14,794 $444 $3,823 $3,938 $13,733 $11,144 $87,563 Forecast Estimate to Cost at Complete Completion (13) (14) $4,449 $9,581 $887 $20,200 $3,101 $8,357 -$3,716 $10,519 $1,753 $7,128 -$4,767 $11,311 $14,777 $28,874 $14,017 $35,881 $6,669 $25,693 $8,516 $26,705 $12,216 $32,801 -$3,887 $4,726 $11,830 $36,000 $2,145 $33,530 $67,990 $291,306 $5,132 $19,313 $5,256 $14,235 $5,375 $16,078 $14,097 $21,864 $19,024 $18,189 $20,585 $8,613 $24,170 $31,385 $223,316 -$60,831 -$21,777 -$23,072 -$6,533 -$14,583 -$11,543 -$56,325 $3,808 -$2,497 $16,430 $907 -$22,705 -$11,236 $13,736 -$196,222 1.12 0.91 2.60 1.03 0.17 0.76 1.69 0.60

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Basic Accounting Auditing Concepts Internal Auditing And Guiding

Authors: Bertram Bessette

1st Edition

B09PMFWVSJ, 979-8796265253

More Books

Students also viewed these Accounting questions

Question

1. Identify three approaches to culture.

Answered: 1 week ago

Question

2. Define communication.

Answered: 1 week ago

Question

4. Describe how cultural values influence communication.

Answered: 1 week ago