Your project consists of framing two walls, then install 4 windows ( 2 windows per wall ) and paint the walls. Because the windows are

Your project consists of framing two walls, then install 4 windows (2 windows per wall) and paint the walls.
Because the windows are similar, the installation time declines with repetition (learning curve effect).
If you know it will take your crew 5 hours to install the first window and 4 hours to install the second window, find the project duration.
Note: First calculate "s" using this formula S=log10(T)-log10(K)log10(N)
Next, calculate T3 & T4 using this formula >>
TN=K(NS)
TN= time for the N th installation
K= time for the first installation
S=
Conduct a forward pass and a backward pass and find the critical activities for the following network diagram.
Next, calculate the Free Float for the following activities:
Task B
Task C Task D
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Aided Database Design

Authors: Antonio Albano, Valeria De Antonellis, A. Di Leva

1st Edition

0444877355, 978-0444877352

More Books

Students also viewed these Databases questions

Question

Explain the importance of Human Resource Management

Answered: 1 week ago

Question

Discuss the scope of Human Resource Management

Answered: 1 week ago

Question

Discuss the different types of leadership

Answered: 1 week ago

Question

Write a note on Organisation manuals

Answered: 1 week ago

Question

d. How were you expected to contribute to family life?

Answered: 1 week ago