Your project has a BAC of $80,000, an AC of $52,500, a CPI of 1.1, and an SPI of 0.98. What does this tell you
Your project has a BAC of $80,000, an AC of $52,500, a CPI of 1.1, and an SPI of 0.98. What does this tell you about the project?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A The project is under budget and ahead schedule. option B The project is under budget and behind schedule. option C The project is over budget and ahead schedule. option D The project is over budget and behind schedule