Question
Your project has four activities. Below is the current status of each activity. Activity A was supposed to cost $350,000 when complete. Its costs so
Your project has four activities. Below is the current status of each activity.
Activity A was supposed to cost $350,000 when complete. Its costs so far are $265,000. It is 45% complete. The activity has completed 7 weeks of a planned 15-week schedule.
Activity B is at the end of week 2 of a planned 4-week effort. It is 75% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.
Activity C is finished. It finished 2 weeks late. It cost $200,000 and it was planned to cost $250,000.
Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.
Using these data, calculate the following.
1.Calculate the CV, SV, CPI, and SPI for each activity and the total project.
2.What is your assessment of the project at this time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started