Your project has four activities. Below is the current status of each activity. Activity A was supposed to cost $350,000 when complete. Its costs so

Your project has four activities. Below is the current status of each activity.

Activity A was supposed to cost $350,000 when complete. Its costs so far are $265,000. It is 45% complete. The activity has completed 7 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 75% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.

Activity C is finished. It finished 2 weeks late. It cost $200,000 and it was planned to cost $250,000.

Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.

Using these data, calculate the following.

1.Calculate the CV, SV, CPI, and SPI for each activity and the total project.

2.What is your assessment of the project at this time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting concepts and applications

Authors: Albrecht Stice, Stice Swain

11th Edition

978-0538750196, 538745487, 538750197, 978-0538745482

More Books

Students also viewed these Accounting questions