Your Project has indirect costs of 100 per week with a total of $1,600 at 16 weeks. Your Direct Costs for the Project at
Your Project has indirect costs of 100 per week with a total of $1,600 at 16 weeks. Your Direct Costs for the Project at Normal time and cost are $680.00 at a duration of 16 weeks. Activity Crash Cost Max Crash Time Normal time A 10 1 4 Normal Cost 30 B 70 2 7 C 0 0 1 80 D 30 2 4 BOH 40 E 50 3 5 110 F 200 3 5 90 G 40 1 2 60 H 40 1 2 70 I 0 0 2 140 Project Duration 16 weeks A C F 4 1x 5 Direct Cost at 16 weeks $680.00 D G 1 4 2 ZX B 7 E H 5 2 Maximum Crash Time? Total Direct cost at Maximum Crash Time? What is the Optimum Crash Point Weeks 5 pts. dollars 5 pts. weeks dollars 10 pts.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started