Your project reached the end of month 2 and you have completed Tasks 1,3,4 and 6. You started task 7 but you haven't finished

image text in transcribed image text in transcribed 

Your project reached the end of month 2 and you have completed Tasks 1,3,4 and 6. You started task 7 but you haven't finished it. Your actual cost is $ 40,000.00. Considering the given project information, and using a 50/50 ratio for unfinished tasks, calculate EAC cost task1 $ 10,000.00 task2 $ 20,000.00 task3 $ 5,000.00 task4 $ 3,000.00 task5 $ 8,000.00 task6 $ 4,000.00 task7 $ 30,000.00 M1 M2 M3 M4 M5

Step by Step Solution

3.51 Rating (161 Votes )

There are 3 Steps involved in it

Step: 1

To calculate the Estimate at Completion EAC cost for the project considering the given ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management for Public Health and Not for Profit Organizations

Authors: Steven A. Finkler, Thad Calabrese

4th edition

133060411, 132805669, 9780133060416, 978-0132805667

More Books

Students also viewed these General Management questions

Question

What are your current research studies?

Answered: 1 week ago

Question

Unequal status relationships lead to a stable society.

Answered: 1 week ago