Your project sponsor comes to you shortly after you completed your scope statement, WBS, and activity list and asks you about how long you think
Your project sponsor comes to you shortly after you completed your scope statement, WBS, and activity list and asks you about how long you think the project will take based on what you currently know about it. You collect a least time (O), most likely (M), and most time (P) estimate. Which estimating technique are you using to answer the project sponsor's