Question

1 Approved Answer

Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and

Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.

Baseline

Activity Name

Start

(Baseline)

Finish

(Baseline)

Cost

(Baseline)

Product

6/2/14

5/25/15

Requirements

6/2/14

8/22/14

60,000.00

Design

8/25/14

11/14/14

90,000.00

Build

11/17/14

3/20/15

120,000.00

Test

3/23/15

5/22/15

50,000.00

Release

5/25/15

5/25/15

0.00

You have to report project status as of January 30, 2015. The associated schedule and cost information is provided below. Assume: (1) a five-day work week; and (2) a constant resource loading (i.e., the rate of planned expenditures is constant over the duration of each activity).

Actual

Activity Name

% Complete

Start

(Actual)

Finish

(Actual)

Cost

(Actual)

Product

6/2/14

NA

Requirements

100

6/2/14

8/30/14

68,000

Design

100

8/31/14

11/20/14

85,000

Build

70

11/21/14

NA

110,000

Test

0

NA

NA

0

Release

0

NA

NA

0

Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.

  1. Earned Value Measures
    1. Calculate earned value measures for each activity and for the cumulative project as of January 30, 2015; fill in the table below:

Activity

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

Requirements

68,000

Design

85,000

Build

110,000

Test

0

Release

0

Entire Project

    1. What is the Budget at Completion (BAC) for the project?
  1. Earned Value Performance Measures
    1. Calculate earned value performance parameters for each activity and for the cumulative project as of January 30, 2015; fill in the table below:

Activity

Schedule Variance (SV)

Schedule Performance Index (SPI)

Cost Variance (CV)

Cost Performance Index (CPI)

Requirements

Design

Build

Test

Release

Entire Project

    1. Is the project ahead of schedule, on schedule, or behind schedule? Why?
    2. Is the project over budget, under budget, or on budget? Why?
  1. Earned Value Forecasts
    1. Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
      1. What is the Estimate at Completion (EAC)?
      2. What is the Estimate-to-Complete (ETC)?
      3. How much more or less money (other than the current budgeted amount) will you need to finish the project?
    2. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Implementing And Auditing The Internal Control System

Authors: D. Chorafas

1st Edition

0333929365, 9780333929360

More Books

Students also viewed these Accounting questions

Question

Describe effectiveness of reading at night?

Answered: 1 week ago

Question

find all matrices A (a) A = 13 (b) A + A = 213

Answered: 1 week ago