Your project will require a 7-day work week rather than the traditional 5-day. How can you adapt the software to this new schedule? Click on
Your project will require a 7-day work week rather than the traditional 5-day. How can you adapt the software to this new schedule? Click on the duration column and add more days to the task. Click on the Project Tab then the Change Working Time Tab Drag the Summary Task line to increase the number of days for task completion The standard calendar cannot be changed