Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Your submittal should include the quantity take-offs and cost estimates presented for both alternatives as shown above in a table format (one table each). Construction

image text in transcribedimage text in transcribed
image text in transcribed
image text in transcribed
Your submittal should include the quantity take-offs and cost estimates presented for both alternatives as shown above in a
table format (one table each).
Construction Cost Estimate Assignment A land developer plans to build a new building on a site that has marginal soil conditions. The geotechnical engineer has identified two alternative foundation systems for this proposed building: Alternative 1: Support the building on pile foundations that extend through the marginal soils into the deeper stronger soils. Alternative 2: Excavate the upper 10 feet of soil and replace it as a compacted fill. The proposed building may then be supported on spread footing foundations founded on the compacted fill. Both alternatives will use a slab-on-grade floor. In addition, both aiternatives will produce a foundation system with equal quality and reliability, and the construction time will be about the same. Neither will require any future maintenance. Thus, the only consideration in selecting the final design is the respective cost of the foundation construction. The structural engineer developed preliminary design drawings for both alternatives, and these drawings show the following: - The proposed building will be rectangular with plan dimensions of 150ft by 200ft. It will have 36 interior columns and all of the perimeter walls will be bearing walls. - For Alternative 1, each column will require four piles, each of which must be 25ft long. In addition, each column will require a 553ft reinforced concrete pile cap. The exterior bearing walls will require 25ft long piles at 10ft on center, and a 22ft reinforced grade beam along the base of the wall. - For Alternative 2, each column will require a 10103ft reinforced concrete spread footing, and the exterior bearing walls will require a 32ft reinforced concrete continuous spread footing. The civil engineer developed a preliminary site plan and grading plan. For Alternative 2, the excavation and recompaction will extend 10ft beyond the building footprint, as recommended by the geotechnical engineer. The civil engineer also determined that Alternative 2 will require 1500 cubic yards of import fill to make up for the shrinkage that will occur during the excavation and recompaction process. Develop hand-drawn sketches of each alternative showing the relevant items needed to develop the cost estimate. Include relevant dimensions. The unit cost information is as follows: Compute the construction quantity take offs and develop construction cost estimates for both alternatives. Present this information using the following format (just an example here): Based on the results of this analysis, recommend a course of action. Construction Cost Estimate Assignment A land developer plans to build a new building on a site that has marginal soil conditions. The geotechnical engineer has identified two alternative foundation systems for this proposed building: Alternative 1: Support the building on pile foundations that extend through the marginal soils into the deeper stronger soils. Alternative 2: Excavate the upper 10 feet of soil and replace it as a compacted fill. The proposed building may then be supported on spread footing foundations founded on the compacted fill. Both alternatives will use a slab-on-grade floor. In addition, both aiternatives will produce a foundation system with equal quality and reliability, and the construction time will be about the same. Neither will require any future maintenance. Thus, the only consideration in selecting the final design is the respective cost of the foundation construction. The structural engineer developed preliminary design drawings for both alternatives, and these drawings show the following: - The proposed building will be rectangular with plan dimensions of 150ft by 200ft. It will have 36 interior columns and all of the perimeter walls will be bearing walls. - For Alternative 1, each column will require four piles, each of which must be 25ft long. In addition, each column will require a 553ft reinforced concrete pile cap. The exterior bearing walls will require 25ft long piles at 10ft on center, and a 22ft reinforced grade beam along the base of the wall. - For Alternative 2, each column will require a 10103ft reinforced concrete spread footing, and the exterior bearing walls will require a 32ft reinforced concrete continuous spread footing. The civil engineer developed a preliminary site plan and grading plan. For Alternative 2, the excavation and recompaction will extend 10ft beyond the building footprint, as recommended by the geotechnical engineer. The civil engineer also determined that Alternative 2 will require 1500 cubic yards of import fill to make up for the shrinkage that will occur during the excavation and recompaction process. Develop hand-drawn sketches of each alternative showing the relevant items needed to develop the cost estimate. Include relevant dimensions. The unit cost information is as follows: Compute the construction quantity take offs and develop construction cost estimates for both alternatives. Present this information using the following format (just an example here): Based on the results of this analysis, recommend a course of action

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management and Cost Accounting

Authors: Alnoor Bhimani, Charles T. Horngren, Srikant M. Datar, Madhav V. Rajan

6th edition

1292063467, 978-1292063461

More Books

Students also viewed these Accounting questions

Question

Review the history of forensic psychology in the United States.

Answered: 1 week ago