Your team has created the following product backlog. Assume that the stories are independent: they each contribute business value and can be built in any
Your team has created the following product backlog. Assume that the stories are independent: they each contribute business value and can be built in any order. Further, assume that the estimates are in ideal days and that the team has the capacity to complete thirty ideal days of work per sprint. Based on this, please answer the questions below.
Story | Priority | Estimate | Planned Sprint (based on capacity) |
Story 1 | 8 | 3 | |
Story 2 | 10 | 2 | |
Story 3 | 1 | 3 | |
Story 4 | 9 | 1 | |
Story 5 | 15 | 2 | |
Story 6 | 11 | 3 | |
Story 7 | 2 | 4 | |
Story 8 | 19 | 2 | |
Story 9 | 22 | 2 | |
Story 10 | 4 | 2 | |
Story 11 | 18 | 3 | |
Story 12 | 7 | 2 | |
Story 13 | 3 | 2 | |
Story 14 | 20 | 2 | |
Story 15 | 14 | 2 | |
Story 16 | 21 | 4 | |
Story 17 | 13 | 2 | |
Story 18 | 5 | 3 | |
Story 19 | 16 | 2 | |
Story 20 | 17 | 3 | |
Story 21 | 12 | 4 | |
Story 22 | 6 | 3 | |
56 |
Question 1: Allocate stories to Sprint 1 using the agile sprint-by-sprint planning approach, being sure to respect the thirty-day capacity constraint.
Allocate the remaining stories to additional sprints, using hybrid release planning.
Question 2:
Determine how many sprints this should take, assuming the estimates are correct.
Question 3:
Based on the assumptions provided previously, which makes more sense to use: agile sprint-by-sprint planning or hybrid release planning? Justify your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started