Your vice president asked you what the Earned Value will be for a small project you are working on. You were given a budget of
Your vice president asked you what the Earned Value will be for a small project you are working on. You were given a budget of $30,000, and to date you have spent $20,000 but only completed $10,000 worth of work. what is the EV amount? Question 13 options: a) $30,000 b) $20,000 c) $10,000