You're given a project, but the Executive hasn't developed the scope statement. What do you do? Choose only ONE best answer. A Wait for them
You're given a project, but the Executive hasn't developed the scope statement. What do you do? Choose only ONE best answer. A Wait for them to develop a scope statement B Negotiate a deadline for when they will get the scope statement to you C Develop a draft scope statement and validate it with the Sponsor and/or Executive D Call a meeting with your project team to develop the scope statement together