Question
You're working on the Office Building project. You are the project manager and creating a status report today. Today is the end of the 10th
You're working on the Office Building project. You are the project manager and creating a status report today. Today is the end of the 10th day. The project budget is estimated as $100,000. It has costed the project $50,000. You've planned to finish $60,000 amount of work so far. You've completed $35,000 amount of work so far. Calculate the followings, show calculation and provide conclusion statement in plain English. 1) Current Month, BAC, AC, PV, EV 2) AT, ST 3) CV, SV 4) TV 5) CPI, SPI, CSI 6) PC, Percent Overrun, Burn Rate 7) ETC, EAC, VAC 8) TCPI