You've just been assigned the job of setting up a product assembly line with the following tasks. Task A B C D E F
You've just been assigned the job of setting up a product assembly line with the following tasks. Task A B C D E F G Time (Minutes) 0.1 0.6 0.8 0.4 1.0 0.3 0.8 Predecessors None A B B, E A D C, F Suppose management wants to assemble 450 units of the product per day. (a) What would our cycle time have to be? (Assume 1 day = 9 hours) (b) What is the theoretical minimum number of workstations for this problem? (c) Construct an AON network for this project. (d) Assign tasks to workstations in order of the largest positional weight (PW), and when there is a tie (two or more candidate tasks have the same PW), break the tie by assigning tasks to workstations in order of the shortest operating time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
The image presents a set of tasks A to G each with a specified time to complete in minutes and a list of predecessors for each task This is a scheduli...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started