Question
1 Approved Answer
Z (+) 0.96 0.97 0.98 0.99 1.00 Probability (Pr) (%) 83.15 83.40 83.65 83.89 84.13 Activity to tm tp 1-2 6 9 12 1-3 3
Z (+) | 0.96 | 0.97 | 0.98 | 0.99 | 1.00 |
Probability (Pr) (%) | 83.15 | 83.40 | 83.65 | 83.89 | 84.13 |
Activity | to | tm | tp |
1-2 | 6 | 9 | 12 |
1-3 | 3 | 4 | 11 |
2-4 | 2 | 5 | 14 |
3-4 | 4 | 6 | 8 |
3-5 | 1 | 1.5 | 5 |
2-6 | 5 | 6 | 7 |
4-6 | 7 | 8 | 15 |
5-6 | 1 | 2 | 3 |
Determine for given activities :
1. Critical path using PERT.
2. Calculate variance and standard deviation for each activity.
3. Calculate the probability of completing the project in 26 days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started