The number of people required for each activity is shown in the following table. The duration of individual activities cannot be altered by the allocation
The number of people required for each activity is shown in the following table. The duration of individual activities cannot be altered by the allocation of additional people, nor may activities be divided into smaller components performed at different times. Activity People Required Per Day
1-2 6
1-3 4
1-4 7
1-6 3
2-6 2
3-5 1
3-7 1
4- 5 5
4-8 6
5-9 4
6- 9 3
7-9 2
8-9 3
(iii) Neatly sketch a sequenced bar chart, not a Gantt chart, for the above project with all activities shown at their earliest start times.
(iv) Indicate the number of people required on each day of the project with all activities at their earliest start times.
(v) By utilizing the floats in the various activities, smooth the daily requirement for people as much as possible. What is the minimum ceiling of people required to complete the project in minimum time? Justify your answer by redrawing the bar chart and indicating the people required on each day.
Step by Step Solution
3.32 Rating (158 Votes )
There are 3 Steps involved in it
Step: 1
iii Neatly Sketch a Sequenced Bar Chart Not a Gantt Chart for the Above Project with All Activities ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started