Zack Manufacturing Company makes a product that is processed through two departments: cutting and final. All materials are added in the first department. During the

Zack Manufacturing Company makes a product that is processed through two departments: cutting and final. All materials are added in the first department. During the month of March 2019, the company made 4,400 units of the product. Standard costs and actual costs for materials and labor are given below:

STANDARD COSTS
Raw materials
Framing: 11 square feet at $0.30 per square foot $ 3.30
Filler: 14 pounds at $0.25 per pound 3.50
Standard materials cost per unit $ 6.80
Direct labor
Cutting dept.: 1.0 hour at $15.00 per hour $ 15.00
Final dept.: 0.60 hour at $16.00 per hour 9.60
Standard direct labor cost per unit $ 24.60

ACTUAL COSTS
Raw materials
Framing: 46,000 square feet at $0.31 per square foot $ 14,260.00
Filler: 62,200 pounds at $0.23 per pound 14,306.00
Total actual materials cost $ 28,566.00
Direct labor
Cutting dept.: 4,300 hours at $15.30 per hour $ 65,790.00
Final dept.: 2,900 hours at $15.80 per hour 45,820.00
Total actual direct labor cost $ 111,610.00

Required:

  1. Prepare a comparison of the actual cost of materials with the standard cost of materials for the 4,400 units of product. Then prepare an analysis of the materials variances.
  2. Prepare a comparison of the actual cost of labor with the standard cost of labor for the 4,400 units of product. Then prepare an analysis of the labor variances.

Analyze: What total variance in labor was reported by the final department?

Prepare a comparison of the actual cost of materials with the standard cost of materials for the 4,400 units of product. Then prepare an analysis of the materials variances.

ZACK MANUFACTURING COMPANY
Analysis of Materials Variances
For Month of March 2019
Costs Variances
Cost Elements Standard Actual Quantity Price
Framing
Standard
Actual
Quantity variance
Price variance
Filler
Standard
Actual
Quantity variance
Price variance
Totals $0 $0 $0 $0

Prepare a comparison of the actual cost of labor with the standard cost of labor for the 4,400 units of product. Then prepare an analysis of the labor variances.

ZACK MANUFACTURING COMPANY
Analysis of Labor Variances
For Month of March 2019
Costs Variances
Cost Elements Standard Actual Quantity Price
Cutting Department
Standard
Actual
Time variance
Rate variance
Final Department
Standard
Actual
Time variance
Price variance
Totals $0 $0 $0 $0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions