Question

1 Approved Answer

Zeui Company's material requirement for 1 year is 20,000 units. Ordering cost for each order is Rp. 500,000. Carrying cost is Rp. 20,000 / unit.

Zeui Company's material requirement for 1 year is 20,000 units. Ordering cost for each order is Rp. 500,000. Carrying cost is Rp. 20,000 / unit. The lead time is 14 days. Question: A. Calculate the EOQ and inventory costs when EOQ! B. Also calculate the inventory cost for 10 and 30 orders! C. If the average usage per day is 55 units and the maximum usage per day is 75 units, then calculate the safety stock and ROP!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Robert K. Eskew, Daniel L. Jensen

5th Edition

0070213550, 978-0070213555

More Books

Students also viewed these Accounting questions

Question

Define Decision making

Answered: 1 week ago

Question

What are the major social responsibilities of business managers ?

Answered: 1 week ago

Question

What are the skills of management ?

Answered: 1 week ago