Zia Homes is contracted to frame 3 2 wooden houses of the same design in a new subdivision of 3 0 0 homes. The fourth

Zia Homes is contracted to frame 32 wooden houses of the same design in a new subdivision of 300 homes. The fourth unit took 420 hours, but the company expects to cut about 10% off the time for each replication of the same design. Use the learning curve assumption of a constant decrease with each doubling of production to estimate past completion times (units 1 and 2) and the completion time for units 8 and 32. Round to the nearest hour.
The completion time for unit 1 was
hours.
The completion time for unit 2 was
hours.
The completion time for unit 8 is
hours.
The completion time for unit 32 is
hours.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions

Question

3. How do your personal interests impact these choices?

Answered: 1 week ago