Question
Zita Ltd has supplied the following data concerning one of its contracts: Contract price N$200 000 Cost incurred to date N$115 000 Estimated cost to
Zita Ltd has supplied the following data concerning one of its contracts:
Contract price N$200 000
Cost incurred to date N$115 000
Estimated cost to complete the contract N$ 37 000
Value of work certified by architect N$120 000
Progress payments received from client N$100 000
Cost of work certified N$ 84 000
- Calculate what amount of profit should be taken on the contract using the work certified method.
- Calculate what amount of profit should be taken on the contract using the percentage completion method.
Step by Step Solution
3.43 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
To calculate the profit using the work certified method we first need to determine the total cost of ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Financial Reporting and Analysis
Authors: Flawrence Revsine, Daniel Collins, Bruce, Mittelstaedt, Leon
6th edition
9780077632182, 78025672, 77632184, 978-0078025679
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App