7.2. For Problem 6.5 using the samples 4160 from the previous chapter, you are asked to estimate...

Question:

7.2. For Problem 6.5 using the samples 41–60 from the previous chapter, you are asked to estimate the process capability. Discuss how you would estimate the short-term standard deviation of the process, e.g., would you exclude the out-of-control ranges?

Why or why not? Calculate the Cp, Cpk and Ppk for the process. Compare these and discuss any differences among them.