A construction project is broken down into the following 10 activities: Activity Immediate Predecessor Time (weeks) 1

Question:

A construction project is broken down into the following 10 activities:

Activity Immediate Predecessor Time (weeks)

1 — 4 2 1 2 3 1 4 4 1 3 5 2, 3 5 6 3 6 7 4 2 8 5 3 9 6, 7 5 10 8, 9 7

a. Draw the network diagram.

b. Find the critical path.

c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?LO5-1

Step by Step Answer: