Braggs Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need

Question:

Bragg’s Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed.

Activity Predecessor Normal Time Crash Time Expediting Cost/Week

(weeks) (weeks)
A — 9 6 $3,000 B A 8 5 3,500 C A 15 10 4,000 D B, C 5 3 2,000 E C 10 6 2,500 F D, E 2 1 5,000

a. Draw the project diagram.

b. What is the normal project length?

c. What is the project length if all activities are crashed to their minimum?

d. Bragg’s loses $3,500 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,500?LO5-1

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: