In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and
Question:
In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week.
Week Number Item J 0 1 2 3 4 5 Gross requirements 75 50 70 On-hand 40 Net requirements Planned-order receipt Planned-order release 10001w