Plan production for the next year. The demand forecast is: spring, 20,000; summer, 10,000; fall, 15,000; winter,

Question:

Plan production for the next year. The demand forecast is:

spring, 20,000; summer, 10,000; fall, 15,000; winter, 18,000. At the beginning of spring you have 70 workers and 1,000 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of summer and the number hired at the start of fall should result in planned production levels for summer and fall that equal the demand forecasts for summer and fall, respectively. If demand exceeds supply, use overtime in spring only, which means that backorders could occur in winter. You are given these costs: hiring, $100 per new worker;

layoff, $200 per worker laid off; holding, $20 per unit-quarter;

backorder cost, $8 per unit; straight-time labor, $10 per hour;

overtime, $15 per hour. Productivity is 0.5 unit per worker hour, eight hours per day, 50 days per quarter. Find the total cost.

W101

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: