The following activities are part of a project to be scheduled using CPM: Activity Immediate Predecessor Time
Question:
The following activities are part of a project to be scheduled using CPM:
Activity Immediate Predecessor Time (weeks)
A — 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G E, F 7
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?