The following activities are part of a project to be scheduled using CPM:

Activity Immediate Predecessor Time (weeks)

A — 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G E, F 7

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. How much slack does activity B have?