The following production flow shows Parts E, I, and N; Subassembly O; and the final assembly for
Question:
The following production flow shows Parts E, I, and N; Subassembly O; and the final assembly for Product P.
A to B to C to D to E F to G to H to I J to K to L to M to N E and I to O N and O to P B involves a bottleneck operation, and M involves a CCR.
a. Draw the process flow.
b. Where would you locate buffer inventories?
c. Where would you place inspection points?
d. Where would you stress the importance of quality production?WT-202