The following production flow shows Parts O, Q, and T; Subassembly U; and the final assembly for
Question:
The following production flow shows Parts O, Q, and T; Subassembly U; and the final assembly for Product V:
M to N to O P to Q R to S to T O and Q to U U and T to V N involves a bottleneck operation, and S involves a capacity-constrained resource. Draw the process flow.