The following table gives the operation times and due dates for five jobs that are to be processed on a machine. Assign the jobs according to the shortest operation time and calculate the mean flow time.
(Answer in Appendix E)
Job Processing Time Due Date (Days Hence)
101 6 days 5 Job Processing Time Due Date (Days Hence)
102 7 days 3 103 4 days 4 104 9 days 7 105 5 days 2WT-202