The second change to consider would be to select the suppliers during subproject P and have them

Question:

The second change to consider would be to select the suppliers during subproject P and have them work directly with the dedicated teams as described in step 4. This would involve adding an additional activity to subproject P called supplier selection and contract negotiation (P5)

with a duration of 12 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would take to complete the project if this additional change were made?LO5-1