1. A project has the following activities, times, and precedence relationships: Activity Time (Weeks) Preceding Activities A...
Question:
1. A project has the following activities, times, and precedence relationships: Activity Time (Weeks) Preceding Activities A 3 none B5 A C3 A D4 B E8 C F 2 D, E
a. Draw a precedence diagram for the project.
b. Calculate the earliest start and finish times for each of the activities.