3. A project has the following activities, times, and precedence relationships: Activity Time (Weeks) Preceding Activities A

Question:

3. A project has the following activities, times, and precedence relationships: Activity Time (Weeks) Preceding Activities A 3 none B 5 none C 3 none D 4 A, B E 8 A, B F 2 D, E

a. Draw a precedence diagram for the project.

b. Calculate the earliest start and finish times for each of the activities.