5. A project has the following activities, times, and precedence relationships: Activity Time (Days) Preceding Activities A
Question:
5. A project has the following activities, times, and precedence relationships: Activity Time (Days) Preceding Activities A 15 none B5 A C 21 A D9 A E 12 B, D
a. Draw a precedence diagram for the project.
b. Compute the earliest start times, earliest finish times, latest start times, latest finish times, and slack times. Write these values in the precedence diagram.
c. Determine the critical path.
d. How long is this project estimated to take?
e. Construct a basic Gantt chart for this process.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Supply Chain Management From Vision To Implementation
ISBN: 9781292022192
Pearson New International Edition
Authors: Stanley E. Fawcett; Lisa M. Ellram; Jeffrey A. Ogden
Question Posted: