7. A project has the following activities, times, and precedence relationships: Activity Time (Months) Preceding Activities A
Question:
7. A project has the following activities, times, and precedence relationships: Activity Time (Months) Preceding Activities A 2 none B 8 none C 3 none D6 B E5 C F 4 B, A G 1 D, E H2 C I 2 F, G J 7 D, C, A K 3 J, I L 6 B, H, I M1 D N 5 K, L
a. Draw a precedence diagram for the project.
b. Compute the earliest start times, earliest finish times, latest start times, latest finish times, and slack times. Write these values in the precedence diagram.
c. Determine the critical path.
d. How long is this project estimated to take?
e. If the project needs to be shortened, should managers focus their attention on activity G? Why or why not?
f. Construct a basic Gantt chart for this project.
Step by Step Answer:
Supply Chain Management From Vision To Implementation
ISBN: 9781292022192
Pearson New International Edition
Authors: Stanley E. Fawcett; Lisa M. Ellram; Jeffrey A. Ogden