Question:

1. Calculate the number of kanbans needed at the ABC Company for the following two products, produced in a factory that works eight hours per day, five days per week:

Product 1 Product 2 Usage 300/week 150/day Lead time 1 week 2 weeks Container size 20 units 30 units Safety stock 15 percent 0