Question:

1. Excelsior Springs Ltd. schedules production of one end product, Hi-Sulphur, in batches of 80 units whenever the projected ending inventory balance in a quarter falls below 10 units. It takes one quarter to make a batch of 80 units. Excelsior currently has 30 units on hand. The sales forecast for the next four quarters is:

Quarter 1 2 3 4 Forecast 20 70 70 20

a. Prepare a time-phased MPS record showing the sales forecast and MPS for Hi-Sulphur.