13. As part of the final assembly process, Leone (problems 11 and 12) decides to dye underwear...
Question:
13. As part of the final assembly process, Leone (problems 11 and 12)
decides to dye underwear to particular colors and replace decals with silk screening. The company invests in the dye and silk screen capacity before checking on the reduction in the safety stock. Assembly lead time increases to two hours. What are the safety stock requirements, given that the company holds no limits on safety stock per option? Does its ability to offer a full product line change?