13. Complete the following MRP time-phased record: Week Item: Toaster 1 2 3 4 5 6 7...

Question:

13. Complete the following MRP time-phased record:

Week Item: Toaster 1 2 3 4 5 6 7 8 Gross requirements 20 20 35 25 35 35 35 35 Scheduled receipts 50 Projected available balance 10 Planned order release Q = 50; LT = 2; SS = 5.

The following events occurred during week 1:

1. Actual demand during week 1 was only 5 units.

2. A scheduled receipt of 45 was received during week 1.

3. A cycle count of on-hand units showed 17 units at the start of week 1.

4. Marketing forecasted that 40 toasters would be required in week 9.

Update the record below after rolling through time.

Week Item: Toaster 2 3 4 5 6 7 8 9 Gross requirements 20 25 25 35 35 35 35 Scheduled receipts 50 Projected available balance Planned order release Q = 50; LT = 2; SS = 5.

218 Chapter 6 Material Requirements Planning

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management

ISBN: 9780073377827

6th Edition

Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann

Question Posted: