14. On a busy day in June, the Framkrantz Factory had five jobs lined up for processing...
Question:
14. On a busy day in June, the Framkrantz Factory had five jobs lined up for processing at machine center 1. Each job went to machine center 2 after finishing at machine center 1. After that they had different routings through the factory. It’s now shop day 83 and due dates have been established for each job. Machine time includes setup time, but it takes one day to move between centers and two days of queue time at each center after machine center 1 (including Finish).
Machine Center Sequence for the Jobs and Days of Machine Shop Day = 83 Time Required Job 1 2 3 4 5 Finish Due Date A 1 4 X 102 B 3 2 8 X 123 C 3 8 2 X 104 D 6 2 1 2 X 98 E 4 1 8 3 X 110
a. Use a spreadsheet program to calculate the priorities for each job using the critical ratio rule.
b. All jobs were at machine 2 by the morning of shop day 96. (Job A took 2 days instead of 1 and job D took 1 day instead of 6 on machine 1.) Unfortunately, there was a long job on machine 2 and none of the five jobs had started yet. What would their priorities be for machine 2?
c. What would priorities be if job A’s due date were 96 (current date 96)?
Step by Step Answer:
Manufacturing Planning And Control For Supply Chain Management
ISBN: 9780073377827
6th Edition
Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann