17. Howies Handicraft needs your advice on the production schedule for its Halloween product line. Analyze the

Question:

17. Howie’s Handicraft needs your advice on the production schedule for its Halloween product line.

Analyze the information for the three-station four-product line, given next:

302 Chapter 8 Production Activity Control Estimated Weekly Selling Material Process Time Sales, Price, Cost, Workstation*

Product (Units) ($) ($) 1 2 3 Witches 60 35 15 10 10 40 Goblins 50 40 15 10 15 40 Ghosts 40 45 20 10 10 20 Ghouls 30 50 20 15 20 20

*The times for workstations 1, 2, and 3 are in minutes per unit. Capacity at each workstation is 2,400 minutes/week and operating expenses are $2,000/week.

a. What is the bottleneck workstation? What schedule of products at this work station maximized the profit to Howie?

b. What is the total profit from the schedule in part a?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management

ISBN: 9780073377827

6th Edition

Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann

Question Posted: