=+2. Consider the following project activities: ACTIVITY DURATION (DAYS) PREDECESSORS A 1 None B 2 None C

Question:

=+2. Consider the following project activities:

ACTIVITY DURATION

(DAYS) PREDECESSORS A 1 None B 2 None C 1.5 None D 3 A, B E 2.5 C F 1.5 D, E G 4 F H 2 F